56662 REL 75: 2008-458-00 EXP STEELHEAD KELT RECONDITIONING |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
All administrative tasks fulfilled with timely quality products | B: 119. Manage and administer 2016 upper Columbia kelt reconditioning project | 01/31/2017 | 01/31/2017 | |
Environmental Compliance Documentation | C: 165. ESA compliance for project implementation | 01/31/2017 | 01/31/2017 | |
2015 Progress Report | D: 132. Submit progress report for the period (1/2015) to (12/2015) | 03/15/2016 | 03/15/2016 | |
Kelts for the reconditioning project | E: 66. Temporary tributary weirs - SF Gold Cr., Beaver Cr., and Hancock Springs | 06/15/2016 | 06/15/2016 | |
Kelts for the reconditioning project | F: 66. Temporary tributary weir - Little Bridge Cr. | 06/15/2016 | 06/15/2016 | |
Kelts for reconditioning project | G: 66. Steelhead broodstock collection and live spawning | 06/30/2016 | 06/30/2016 | |
Functional Kelt Facility | H: 61. Methow Steelhead Kelt Facility (MSKF) operation | 01/31/2017 | 01/31/2017 | |
Reconditioned Kelts | I: 176. Steelhead kelt reconditioning | 01/31/2017 | 01/31/2017 | |
Kelts for reconditioning project | J: 66. Kelt Collection at Rock Island Dam | 06/30/2016 | 06/30/2016 | |
Tagged kelts | K: 158. PIT and radio tag kelts | 10/31/2016 | 10/31/2016 | |
Submit BiOp RPA Report in Taurus | L: 202. BiOp RPA Report for CY 2015 | 02/15/2016 | 02/15/2016 |
Primary Focal Species | Work Statement Elements |
---|---|
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 02/01/2016 | ||||||
B | 119 | Manage and administer 2016 upper Columbia kelt reconditioning project | 02/01/2016 | ||||||
C | 165 | ESA compliance for project implementation | 02/01/2016 | ||||||
D | 132 | Submit progress report for the period (1/2015) to (12/2015) | 02/01/2016 | ||||||
E | 66 | Temporary tributary weirs - SF Gold Cr., Beaver Cr., and Hancock Springs | 03/24/2016 | ||||||
F | 66 | Temporary tributary weir - Little Bridge Cr. | 03/24/2016 | ||||||
G | 66 | Steelhead broodstock collection and live spawning | 03/24/2016 | ||||||
H | 61 | Methow Steelhead Kelt Facility (MSKF) operation | 02/01/2016 | ||||||
I | 176 | Steelhead kelt reconditioning | 03/24/2016 | ||||||
J | 66 | Kelt Collection at Rock Island Dam | 03/24/2016 | ||||||
K | 158 | PIT and radio tag kelts | 03/24/2016 | ||||||
L | 202 | BiOp RPA Report for CY 2015 |